Copley bridge set to reopen this week
The Cleveland-Massillon Road bridge over Wolf Creek is set to reopen five months after it was closed.The bridge spanning Barberton’s drinking water...
Busy Copley bridge expected to reopen next month
The Cleveland-Massillon Road bridge over Wolf Creek is expected to reopen in late September — weather permitting, of course.The heavily traveled bridge,...
Summit County decides to replace Cleveland-Massillon Road bridge
The Summit County Engineer’s Office plans to hire Ruhlin Co. of Sharon Township this week to replace the Cleveland-Massillon Road bridge over...
Ruhlin Replaces 178-Year-Old Dam
The $33 million construction of a new East Reservoir dam for the Ohio Department of Natural Resources (ODNR) in Portage Lakes State...
East Reservoir Dam project progressing
As 2018 comes to an end, soil-cement drilling will conclude along three embankments — the south embankment, the main embankment and the...